Brief
Fabricate & Install 3” nb Cooling Water, 1” nb Compressed Air, 6” nb Sour Liquor & 4″ NB Nitrogen lines onto a 50m Long Skid. Re-design, fabricate and install 4″ steam pipework. This involved extensive fabrication, testing and commissioning of approx. 1000m of pipeline.

The skid was then lifted into position to enable ERS to connect all the lines to existing supply framework.

The project was undertaken over a 6-month period.

Specifications
Pipe Steel Grade P235GH
Piping: BS EN ISO 13480
Welding: BS EN ISO 15614-1
Welding Process: TIG / MMA